Tuesday, June 29, 2021 - Update:
- There were some slight delays in the concrete portion of the project as some equipment issues were met
- Work is currently underway along both the east and west sides of the street at the south end of 53 Street by the hospital and funeral home. Base work is being completed and forms are being placed.
- Due to the extreme heat, no concrete will be poured until Monday, July 5.
- The road is open for through traffic, please proceed with caution.